on 05-29-2014 2:26 PM
Hi,
We are starting a new upgrade from AC5.3 to AC 10.1 project. In migration document it mentioned that we can migrate CUP requests transactional data to 10.1.
our management is asking to maintain the CUP transaction data in AC10.1 application for future reference for auditing requirements. After closing of all old CUP requests we need to migrate CUP Requests Data into 10.1.
Is it possible? If possible, Please let me know if there are any challenges from your experience from your upgrade projects of same requirement.
Thanks,
Sathish.
We tested in a poc system. Its working...we migrated CUP requests transactional data to 10.1
Thanks,
Ram.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.