Question on stock generation with rounding value during MRP

Former Member
0 Kudos

Hello experts,

Can you help me know if the following scenario is possible in standard MRP customizing?

Our vendor sells 100 units at a time.
Therefore Rounding Value is set to 100.
We set "lot size" : WB (1 week)

In first week requirement is spread as 20, 30, 40 ==> total 90.
Therefore, PR with 100 is created (Cause Rounding Value 100).

In Second week net requirement is 110. But MRP execution creates a new PR only for quantity 100 again, as it is considering the excess 10 from the previous week. The requirement here is to have a new PR generated for quantity 200.

Is there any way I can customize MRP to not consider the excess stock from a previous period during order creation?

Please advise.

Thanks & regards,

Deepthi