Problem on creating process order

Former Member
0 Kudos

Dear Team,

I have a problem on creating process order thru COR1 where the basic start date only accept and follows current date. Basic finished date, no problem. Previously, i can set the basic start date using previous date / date in the past (in the same current month). I'm using "Only capacity requirements" for scheduling type.

is there anywhere in the SAP config that i can check?

and why this problem occured?

Thanks

Accepted Solutions (0)

Answers (1)

Answers (1)

0 Kudos

Hi,

This question seems to be related to ERP rather than to SAP ME. So, you'd better post it to ERP-related forum. Please use these instructions to find a proper space.