Issue in wrongly delivered material

Former Member
0 Kudos

Hi all ,

Depot got an order from a customer for a material A qty 1000 and while doing delivery by mistake they delivered material A of different size  and it has been consumed by the customer.

Now the physical stock of the material A  at depot is 1000 qty but in SAP system the stock is 0, so how can I take this stock back into the system.

Thanks

vincent samuel

Accepted Solutions (1)

Accepted Solutions (1)

sudeep_a
Active Contributor
0 Kudos

Hi Vincent,

You may do a material to material transfer using movement type 309 from B to A. Please be aware of the impact on FI fir this transaction. If the price control is V (moving average), there is no impact. But if the price control is S (Standard price) there can be an Expense/revenue from stock transfer, which will be posted to the account maintained against transaction 'AUM' in OBYC.

Regards,

Sudeep.

Answers (6)

Answers (6)

Former Member
0 Kudos

Dear Sudeep

Thanks for reply

The material have a standard price so what will be the implications while doing the process  ?

Regards

Vincent

sudeep_a
Active Contributor
0 Kudos

Hi Vincent,

If both materials are having same standard price, then there is no impacts. If it's different, please refer the following example.

Standard price of material A: 10 INR.

Standard price of material B: 12 INR.

when you transfer 1000 Qty from B to A, the following entries will be posted.

Stock account of B : 12000 INR (Cr.)

Stock account of A : 10000 INR (Dr.)

Expense/Revenue from stock transfer : 2000 (Dr.)

Regards,

Sudeep.

Lakshmipathi
Active Contributor
0 Kudos

Moved from SAP ERP Sales and Distribution (SAP SD) to Internationalization and Unicode.  Please post all your CIN related queries here.

G. Lakshmipathi

sudeep_a
Active Contributor
0 Kudos

Dear Lakshmipathi,

I don't think this is related to CIN. Its more or less related to inventory management I guess.

Regards,

Sudeep.

Former Member
0 Kudos

Hi Vincent,

you can alternatively run an inventory to fix differences.

Regards,

JM

Former Member
0 Kudos

Hi Vincent,

Depending upon whether the stock for delivered item(wrong size) is 1000 or 0 the stock for the non delivered item can be changed using material to material transfer(309) or MB1B.


regards

Varun

phanikumar_v3
Active Contributor
0 Kudos

Dear Sudeep --what is material to material transfer??

can you give little more description on this--if possible with relevant examples.

Dear Vincent--your requirement is not understandable.how many sizes are there for one material A??

Phanikumar

Former Member
0 Kudos

Hi Vincent,

Why dont you have the option of material to material transfer using 309 movement type in this case?