Modifying test results after the usage decision has been made?

cristin_charbonneau
Participant
0 Kudos

Hi.  I have to put this question out there even though I'm pretty sure I know the answer. 

Is there any way, user exit / creative workaround, to change inspection values once the usage decision has been made?  Can the lot be cancelled and a unit re-inspected somehow?  My users have closed out several inspections with incorrect values and they need to be changed somehow.

Thanks in advance,

Cristin

Accepted Solutions (1)

Accepted Solutions (1)

cristin_charbonneau
Participant


Thank you all for the suggestions.

In the end, based on OSS note 33924, my abaper has implemented a CMOD project called ZQMUSAGE using enhancement QEVA0008. This will allow the results to be unlocked for corrections and then the UD re-applied.

Thanks!

Cristin

Answers (3)

Answers (3)

lakshmi_prasad7
Contributor
0 Kudos


Note is availble for this business

Former Member
0 Kudos

In MIC, you have the option as "Long term Inspection" in Control Indicators.

This will allow you to edit / change the results even after Usage decision.

jogeswararao_kavala
Active Contributor
0 Kudos

Hi Cristin,

Cancel the UDs executing program RQEVAC50 via SE38.

Jogeswara Rao K