on 05-26-2014 3:06 PM
Hello colleagues,
We're on SAP AFS 6.5, and we are using the Early allocation functionality. We've discovered 2 issues for which we were wondering whether there's a solution:
35. Rescheduling for allocated scheduling lines: Once ARun allocates (R or F), the schedule lines are not touched by ATPor re-scheduling. If there is a change in date of the future stock I e already allocated to the requirement and if you want changed date to be reflected on the requirement the options available are
a) Manually de-allocate the order and allocate it again.
b) Maintaine de-allocation rule at stock level so that any change in thedate of the stock it de-allocates and again allocate it.
My question here is how to perform the option b? I (think I) know how to set up deallocation rules on SO, PO, Confirmations (note that there's no L/AB deallocation functionality!!!), etc, but how to setup deallocation on stock level?
Is there anyone who is able to help me further on both topics?
KR,
Peter
Hello,
Can someone please help?
KR,
Peter
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
99 | |
12 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.