Did you mean: 

Operations and activities missing in PDS in APO

Former Member
0 Kudos

Hi All,

I have create a master receipe in ECC when transfering the same to APO it deesn't have operation and activities.

Resource data is all correct as already there are PDS in APO with same resource having oper/act.

Any idea to resolve this.

Thanks,

Krishna

Accepted Solutions (1)

Accepted Solutions (1)

m_manimaran
Active Contributor
0 Kudos

Hi Krishna,

Please check the control keys assigned to the operations, they should be scheduling relevant. Also, check, the standard values are maintained with the values, which is based on work center formula, not calculated as zero.

Regards,

Manimaran M.

Former Member
0 Kudos

Hi Manimaran,

Thanks for reply.

Control keys are scheduling relevant and std values are maintained.

Thanks,

Krishna

m_manimaran
Active Contributor
0 Kudos

Hi Krishna,

Could you please check if the integration model for the resources is active?

If that is also active, try to re-transfer your PDS once using RIMODINI or CURTO_CREATE transaction w/o selecting the change transfer flag.

Regards,

Manimaran M.

Former Member
0 Kudos

Hi Manimaran,

Thanks a lot.

In hurry i missed that resource integration model was deactivated.

This working now.

Thanks,

Krishna


Answers (0)