on 05-23-2014 11:26 AM
Hi All,
I have create a master receipe in ECC when transfering the same to APO it deesn't have operation and activities.
Resource data is all correct as already there are PDS in APO with same resource having oper/act.
Any idea to resolve this.
Thanks,
Krishna
Hi Krishna,
Please check the control keys assigned to the operations, they should be scheduling relevant. Also, check, the standard values are maintained with the values, which is based on work center formula, not calculated as zero.
Regards,
Manimaran M.