on 03-23-2007 9:32 PM
Hi everyone,
I created a Project A with WBS structure in PS (not statistical WBS structure). And then I assigned a work order to one of the WBS element A.0001. I did not post any cost to the WBS element directly. I only charged $1000 to the work order. Now when I use CN41N to generate the cost report and I found the $1000 in work order rolled up to WBS element A.0001 ($1000 showed at work order level and also WBS element level). Then I settled $1000 in the work order to a WBS element C.0001 in Project C. When I run CN41N again to see the cost in Project A, the $1000 still showed up at work order level, but it did not show up at WBS element level A.0001. I need the cost to roll up at WBS element level also, so this is a big problem for me.
I did several test. Assigned another work order to this WBS element A.0001 and charged another $1000 to the work order. Then I settled them to cost center directly instead of to WBS element. The $1000 showed up at the work order level and also at WBS element level (the cost rolled up from work order to the WBS element in that report). Then I tried to settle to GL account, the cost will roll up to WBS element too.
So I found only when I settle the cost to WBS element, the cost won't roll up. I think it might be a configuration problem. Does anyone know where I need to configure in order to let the cost roll up to the WBS element after I settle the Work order to a WBS elements?
Really appreciate your help!
Ting
Hi Xiong,
OSS note 51971 provides the explanation for this behaviour and a possible workarround.
Hope this helps!
Rgds
Martina
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
91 | |
10 | |
10 | |
6 | |
5 | |
5 | |
5 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.