on 05-20-2014 5:17 PM
Hi All,
We have implemented SRM 7.13 and enable PDP scenarion without PI, maintained views V_T160EX & V-T160PR in ECC and created an entry channel in SRM org structure.We have observed that when a PM workder is created with current date , PR gets transfered to SRM but when date is future date it does not transfer a PR to SRM for SC creation.
Please let me know if you have also faced the same issue and how we can avoid this in our system.
Thanks,
Ankur
Hi Ankur,
Have you scheduled the program BBP_EXTREQ_TRANSFER as a background Job ?
Please check if the variant is configured only to pick the PR`s created on the same day.
Regards,
Suresh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.