Issue in transferring PR from ECC to SRM for PM workorder

Former Member
0 Kudos

Hi All,

We have implemented SRM 7.13 and enable PDP scenarion without PI, maintained views V_T160EX & V-T160PR in ECC and created an entry channel in SRM org structure.We have observed that when a PM workder is created with current date , PR gets transfered to SRM but when date is future date it does not transfer a PR to SRM for SC creation.

Please let me know if you have also faced the same issue and how we can avoid this in our system.

Thanks,

Ankur

Accepted Solutions (0)

Answers (1)

Answers (1)

suresh_murugan
Explorer
0 Kudos

Hi Ankur,

Have you scheduled the program BBP_EXTREQ_TRANSFER as a background Job ?

Please check if the variant is configured  only to pick the PR`s created on the same day.

Regards,

Suresh

Former Member
0 Kudos

Hi Suresh,

We have scheduled the program BBP_EXTREQ_TRANSFER as a background Job in our system and details of the variant is below:

Let me know if i need to make any change in the above details.

Thanks,

Ankur

Former Member
0 Kudos

Hi Ankur,

Does EPRTRANS table gets filled with the PR created with future date ? If yes then the background job should pick those PR.

another thing in the variant can you try to select several queues (X) and execute in background.

Best Regards,