on 05-19-2014 2:31 PM
Hello,
Request inputs for one of my query as follows-
I have created a project and released it. Before budgeting itself, if I am posting costs against to WBS /NWA of the same project, the system accepts and posting costs. I m performing a financial posting. Also, if I check Budget S_ALR reports, I can see variance in NEGATIVE value with ZERO in budget value and some value in Actual costs.
AVAC is active for my project. I tried CJBN/ CJBV and CJEN, but doesn’t worked. Also, both CJBN/CJBV says, AVAC is not active when I run. What could be the reason for this.
Thanks for your time.
Regards,
Sumanth
Hi Sumanth,
If you want system to check budget availability on WBS before actual postings and with zero budget, then implement snote 599813 - Availability control before budgeting
In budget profile enter the activation type as "1" So that AVAC get activated once you enter the budget in CJ30.
If you select activation type as "2" then schedule "CJEN" as background job.hence AVAC will
be activated automatically for existing projects as well as newly created projects.
Regards,
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello Nag,
Thanks you for your response.
I have checked the note and found that, it can be implemented in our system. But, still for already existing projects, we are able to post costs more than the limit that we defined in our system, what could be the reason for this.
Activation type is 1 and also AVAC is active and no exempted cost elements defined but still posting, where the system is going wrong.
Regards,
Sumanth
Hi Sumanth,
Check the posting date of actual cost posted on wbs, whether it was before budget entry in CJ30 or after budgeting. With activation type "1", AVAC will be activated once you enter budget for the first time in CJ30. if the actual cost posted before budget entry, then system might have allowed without AVAC.
Regards,
Hi Sumanth,
Please check the WBS elements are budgeted (system status BUDG) or not. If budget is not there against wbs/s then AVAC will not work for it.
Also, check the tolerance limit is maintained for your current transaction (PR/PO.... ) or whether it is "+" or not.
Please check and confirm.
Regards
Saurabh
Hi Sumanth,
As I could see from the screen shot that you have provided, S_ALR... report shows no budget against project wbs. The system status is BUDG because the budget was allocated earlier but it was removed from the WBS elements. In this case the system status BUDG will not go automatically. You have to run OPSX to recorrect the system status.
Coming to your issue, you have to allocate the budget to the WBS in CJ30 followed by CJBN and CJEN.For budget check it is prerequisite to have atleast a single digit value in CJ30 (except 0) against WBS elements.
Regards
Saurabh
Hi,
Chec the budget profile activation of budget should 1 it should not be blank and post the post for it.
Regards,
Raman
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.