Team,
There is a specific requirement regarding sales order..to analyze the dropped /undelivered order for a period.
Currently we are entering only those sales orders in the system which can be shipped/delivered to customer..all those SOs which can’t be delivered are not entering in system.
It is because if we are entering those orders in the stem, MRP will consider those orders for planning.
Now we need to include all the sales orders in SAP and MRP should only consider such orders which can be shipped. Can we do it in the system?
Thanks for the advise.
Regards,
Vijesh
MRP should only consider such orders which can be shipped. Can we do it in the system?
At what stage, you will come to know that sale order can be shipped as planned? Nevertheless, you can either change the MRP Type in material master to ND or change the schedule line category in sale order to CN so that system will not consider such of those materials for MRP. You have to decide which one is better but I would prefer the second one as changing the master data quite frequently is not recommended.
G. Lakshmipathi
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Does dropped/undelivered mean cancelled? If yes, you can you "Reason for Rejection".
Anyway, I think MRP should consider all sales order (except the rejected/cancelled items - with reason for rejection), so that you can fulfill customer order.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
102 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.