MD04 Pur req Still Exits even next MRP run

Dear All

 

I am facing a problem inMD04 with Pur Req in Production system

we have two plants let say1001 & 1008 and scenario is STO,

The problem actual is production orders that have been completed and closed should not have a residual
requirement left in MD04.

PurRqs Entry for 11/5/14 should have cleared down on the next MRP run, After the order was closed.

 

And this has not happening and does not happen for any of the materials
associated with the production order.

when order is completly close pur req associated with production should be cleared off in MD04.

And again i have ran MD03 keeping planning mode 3 then i can see that Pur Req is cleard off

Kindly please sugggest what has to be done, as we are faced a problem twice.

Best Regards

Vasudeva