Dears

i made all configuration related to MRS that for integration with PM/CS,

demand still not shown in the MRS planning board.

does any one has a full configuration document for MRS ?

Thanks,,

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Thanks Saves

S0022314014
Active Contributor
0 Kudos

Hi Nader

If the demand is not showing up, I suggest you to check the configuration relevant to control keys and order types. SAP configuration document for 8.0 and 9.0 can be found in SAP Marketplace or OSS.

Cheers

Savas

Former Member
0 Kudos

Hi Savas,

Do you have the direct link?

I tried to find the document but no luck.

Regards

Rogerio

S0022314014
Active Contributor
0 Kudos

Hi Rogerio

Assuming this is MRS 9.0 fist go to the following web page:

http://help.sap.com/mrs

Now you will find lots of useful information there but then on the section "Configuration and Deployment Information"  click on SAP Marketplace. (You need OSS user id and Password)

And then download the solution manager document.

In that document you will find the configuration guide.

As some parts of configuration may need the touch of HR (especially for the evaluation paths), you may need some help from HR department.

Make sure that you have applied all of the required OSS notes. (i.e. For activating MRS for PS, you need to apply several OSS notes. Make sure that you have done them all.)

There are at least two batch programs you need to run. Don't forget running them in order to move HR data from HR to MRS in order to be able see your resources.

I hope this will help.

Cheers

Savas

Former Member
0 Kudos

Thank you Savas.