We have implemented a parallel processing solution using the Call Function Starting New Task Destination in Group format to split a large number of updates across an RFC Server Group.

This works well when running the ABAP in dialog, but when we schedule for background processing, the parallel processing does not seem to occur, we get a single background process.

Does anyone have any ideas why this may be occuring ?

Thanks

Paul

replied

The mystery is solved.  It does parallel run as expected in background, but our algorithm for deciding to parallel run or in line run was wrong.