Pricing conditions for the articles are getting triggered one day before the actual activation date to 3rd party systems through job WPMU.

Former Member
0 Kudos


Hi SAP Guru´s,

Currently we are sending the pricing, promotions & article master data delta load to 3rd party system from SAP ECC via SAP XI through IDOCS using daily scheduled batch jobs WPMU. IDOC segment - WP_PLU.

Here the issue is the promotion & pricing data are sent to 3rd party system one day before the actual start date.

Eg: Promotion 123456 which has start date as 15/05/2014 & ending on 30/05/2014 & was created & activated on 13/05/2014.

This promotion 123456 is getting triggered from SAP ECC through batch job on 14/05/2014 morning & 3rd party system receives the data on 14/05/2014 & the promotion are getting activated at 3rd party system end on 14/05/2014 itself which actually gets active from 15/05/2014.

Same in the case for Standard Pricing data which needs to be active from 31/05/2014 once the promotion 123456 ends on 30/05/2014.

The standard pricing data gets triggered from SAP ECC on 30/05/2014 through batch job & reaching 3rd party system on 30/05/2014 & getting activate on 30/05/2014 itself.

This creates more issues at the store end as well as affecting business.

We checked at 3rd party system end & they replied that their system considers the updated time stamp & date to activate the prices & it does not considers the actual active from & active to date. They need the data to be sent from SAP ECC on the effective date of the pricing & promotions.

Can any one help me how to change the pricing conditions beign triggered through batch job in SAP ECC based on the actual promotion & pricing conditons start date or is there any other process to trigger the data through the batch job on the actual promotion & pricing data activation date.

Thanks in Advance.

Thanks & Regards,

P.P.Shankar

3 REPLIES 3

Former Member
0 Kudos

Hi,

I have the same issue ? Did you find the reason of the issue ?

0 Kudos

Hello Shankar,

Change the lead time in the POS Outbound Profile. You can't put less than 2 days there so data for today and tomorrow will be transferred which also means you need to adjust your batch timing accordingly.

Sales and Distribution -> POS Interface -> Outbound -> Maintain Profile for POS Outbound.

See if it helps. The best option would still be that the 3rd part system considers the activtion date.

Kind Regards

Kaizad

0 Kudos

Hi Kaizad,

Thanks for your response.

Thanks & Regards,