Dears,
How can I see when I have planed cost on Activity on Network? In CN60 I can see all changes, but initial adjustment I cannot see. It should exist some transaction or a button inside the Network where I can see when the Activity was created and planed.
I am looking in SAP and I cannot find the answer.
Thank you.
Rodica
Hi,
I don't think existing of such report to display when was activity created and planned. There is no admin tab what we have for WBS elements. You can see through change log using CNS60 if you have activated.
Thanks,
Sudhakar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Sudhakar,
I am 99% sure that there is a transaction or log view where it is possible to track all activities in SAP. It is imposible that such platform as SAP not having this option.
I have a very strange situation with more costs than budget and I need the exact date and time when money were planed on Activity.
All changes are visible in CN60 but only changes (not sure what is CNS60, I will check tommorow in the office).
I am new in SAP PS, but I will study and search until I will find this information. I really apreciate help of all members of this comunity.
Thank you.
Rodica
Hi.
If you would look up change documents of status CREATED. You could see who set the status and when. This happens at creation of the operative activity.
On the activity you click at the blue "i" button, then select in menu Extras --> Change Documents --> All . You double click on system status CRTD created and will see when it was set the first time. This is when the activity was generated.
Change Documnets in CN60 would show which old value later on was replaced by another.
I hope this helps and answers.
BR.
Hi Rodica. I guess there is no such transaction besides CN60. What you see there also depends from settings of the project or network profiles used and other settings, e.g. POs or similar. CN60 really is a good transaction for project system change documents keeping in mind that for initial records a workaround is necessary. BR. Jens
Hi
Check report CN47N.
Regards
Saurabh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Not sure but you can check in Edit->Cost->Plan/Actual->network activity
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
91 | |
10 | |
10 | |
6 | |
5 | |
5 | |
5 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.