Dear All,

Kindly suggest how to populate task list included in maintenance plan (for notifications only) into the tasks tab included in resultant notificaton. I have tried  ''Determine Tasks Function'' but it does not meet our requirements.

If there is any BADI/User Exit for this, please mention.

Regards,

waqas

Accepted Solutions (0)

Answers (2)

Answers (2)

former_member186385
Active Contributor
0 Kudos

Hi,

In the notification type overview

enter Maintenance Plan tab

once you add this, you can see Task list tab  where you can add task list manually

hope you understood

regards,

santosh

Former Member
0 Kudos

Thanks for response santosh,

I do have this tab in my notification but clients requirement is to populate these tasks in TASK tab of notification where he can assign person responsible (PERNR) for each task.

Regards,

waqas

peter_atkin
Active Contributor
0 Kudos

waqas

This data is automatically populated when a notification is created from a maintenance plan.

Also ensure that tab 10\TAB08-Maintenance plan is active for your notification type in the IMG

PeteA

Former Member
0 Kudos

Thanks for response peter,

I do have this tab in my notification but clients requirement is to populate these tasks in TASKtab of notification where he can assign person responsible (PERNR) for each task.

Regards,

waqas

peter_atkin
Active Contributor
0 Kudos

Waqas,

So you want to copy the task list operations into the notification Task tab?

PeteA

Former Member
0 Kudos

Exactly Peter.........

Regards,

waqas

peter_atkin
Active Contributor
0 Kudos

Waqas,

You will need to develop a solution, probably using QQMA0014 (notification SAVE event).

PeteA