on 05-11-2014 9:03 AM
Hi
During EhP4->Ehp7 upgrade the fase MAIN_SHDIMP/PARMVNT_SHD has been running for about 24 hours. I can see in \tmp directory that the import is progressing so things seems to be ok, but slow.
But is there anyway to check the actual progress of this fase - i mean is it 20 hours more or 30 minutes?
Hi SAP is on the issue, and i have restarted the process. But i really don´t know how to see if the process i hanging or if something really is happening.
I not in the mood to wait 20 hours more until i break the process!
By the way i run 3 processes in parallell...
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Be aware that there are bugs in the SUM version 10 and if that is the reason then you probably would have to reset the upgrade and start with a new version of SUM. the version 9 of SUM worked well. In any case suggest you to update the thread with the solution provided by the SAP support.
Good Luck
RB
Hi
Just an update in case other users will have the same issue:
The process was in some kind of endless loop. It was noticed by 3 files where growing and growing in \tmp directory.
In SLOG740 we found
ERROR: Cannot rename C:\usr\sap\VMP\SUM\abap\tmp\PD000510.VMP
ERROR: The process cannot access the file because it is being used by
another process.#
ERROR: tpwritelog: tmp-log C:\usr\sap\VMP\SUM\abap\tmp\PD000510.VMP
could not be removed nor renamed
Solution provided from SAP was to kill the SUM-process (and the tp.exe processes), rename the files mentioned in the SLOG and restart the upgrade.
Things are running ok after that.
But as as note:
I still really have found any good way of telling if things are running ok but slow or if things are stucked. It could be very nice to have some kind of Process list who tells us which process could run for hours/days and which processes should end in minutes.
since the time for each phase is dependent on each client hardware/software configuration the timing can only be get accurate once the first upgrade is completed typically on a SBX system. At the end of the upgrade there is a html file which list the time it took for each phase. Then subsequent systems will be same or faster based on the hardware compare to the SBX system.
Hello
You have the option to make use of the parallelism for few phases during an upgrade.
Check this SAP note understand how it works
1616401 - Understanding parallelism during the Upgrades, EhPs and Support Packages implementations
What matters is the hardware resources. If the hardware has enough CPU and RAM then it will help.
If the logs are getting updated and if the phase is not running in a loop then I would wait.
What is the underlying database you are using ?
Regards
RB
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
How many parallel import jobs did you configure for import? 24 hrs seems high. Impor differs based on the number of parallel import jobs, performance of hardware and db tuning.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
24 hours is generally not normal for this phase.. please check
1960112 - Performance analysis for PARMVNT_SHD phase
1960418 - Trouble shooting for PARMVNT_SHD phase
best regards
ashish
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
93 | |
10 | |
10 | |
9 | |
9 | |
7 | |
6 | |
5 | |
5 | |
4 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.