Hi Gurus,

My client is having 02 appraisal periods dates like "Appraisal validity Period" which is an validity period of appraisal document. And also they are using another period call. " appraisal campaign process period"


i can assign the  validity period but I don't know how to assign the " appraisal campaign process period" in the header area. Are there any way to assign these 2 dates in the header area if the template.


can anyone assist me?


regards

Saritha

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

There are multiple dates available in OSA.

If you open a template in PHAP_CATALOG, goto tabpage "Layout". There you can see checkboxes:

* Do not display validity period

* Do not display Execution period

You can use execution period maybe?