Dear Mates,

I've uploaded two sets of data using PP02 T-code where one is Historical data & the other is Current data. Here for Current data I'm facing a Issue  where Cost center & org unit's data aren't getting updated in IT 0001 & its still showing the Historical data in IT0001. This is even spoiling the show & frustrating, where users are unable to do CATS Reconciliation also. for more clarification kindly find below screenshots.

PO13

We have maintained historical data in system where one cost center is assigned from 01.01.2013 to 31.03.2014 & second cost center is assigned from 01.04.2014 to 31.12.9999 with current period, not only cost center's but also Org unit's are also not updating in the system. I've even tried with RHINTE00,10,20 & 30 program's but still I'm unable to get the desired results.

Historical data from 12.11.2013 to 31.03.2014 in IT0001

Current record 01.04.2014 to 31.12.9999 in IT0001

Kindly let me know how to update IT0001.Is there any std program available to update the data apart from RHINTE**???

Ur's

Mohan

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi Mohan,

Check the integration switch is activated or not.

former_member194940
Active Participant
0 Kudos

Dear Mohan,

Try assigning your cost center to position it will default both your org unit and cost center.

Cheers!