cancel
Showing results for 
Search instead for 
Did you mean: 

Budget exceeded in CJ32

Former Member
0 Kudos

HI

getting Below Error

Item WBS Element XXXXXX Budget exceeded

Message BP604

When  User wants to release the Budget in CJ32 he get the above error

they do Bottom up budget, Period Wise they have assigned the Budget

At first level after total up budget is 90laks, they have released only 16lak, this month they are trying to do release balance amount of 74lak

thy could not able to do, system say budget exceeded

in cj32 when its checked assigned value was 2 cr's which is more the release budget

WBS 4 level XXXXXXX  Budget 1687000  Assigned  1005276

WBS 4 level XXXXXXX  Budget 1900000  Assigned 18466080

WBS 4 level XXXXXXX  Budget 4600000  Assigned     264621

WBS 4 level XXXXXXX  Budget  NA         Assigned   1725420

First thing how system allowed to do commitment/actual booking more then the released Budget when Availability control was active

Kindly advice what are all the changes need to be done

Thanks

Accepted Solutions (0)

Answers (1)

Answers (1)

varshal_kachole3
Active Contributor
0 Kudos

hi,

Please check SAP note http://service.sap.com/sap/support/notes/1606591.

Hope it helps!

Thank you and Regards,

Varshal Kachole