Issue with SC item addition in PO

Former Member
0 Kudos

Hi All,

I am trying to add a SC in PO in this way -

-Edit the PO (already has a service line item)

-Add Item

-Old shopping carts and templates - Search the SC number (it has a service line item), select it and press OK

-It adds a line item in PO but the net quantity and value is 0 and the attachment is no more there (original SC has a valid quantity, value and attachment available)

What could be the possible reason?

Note: Extended Classic Scenario, Shopping cart is in Follow-on Document deleted status.

Thanks and Regards,

Pankaj

Accepted Solutions (0)

Answers (2)

Answers (2)

ImreMatyas
Product and Topic Expert
Product and Topic Expert
0 Kudos

Hey Pankaj,

Maybe the problem comes from the SC status. The Shopping Cart item gets the technical status 'Follow-on document deleted' (I1115). => the request is open again, the corresponding Shopping Cart item is sent to the Sourcing Cockpit, even if the product category is not sourcing relevant.

Can you please check the OSS Note '1649794 - Status dependent control of Shopping Cart', "deletion" part?

Hope my answer was helpful!

Imre


Former Member
0 Kudos

I observed the same issue in our system and this could be a standard system behaviour and dont see any reason why it should be skip the quantity and Price and that is the purpose of copying functionality.

Check any OSS note or write to SAP on this.

Thanks

Balaji

Former Member
0 Kudos

Hi Pankaj,

Were you able solve this issue? If yes,How did you accomplish this?

Thanks

Balaji