How to copy CJ40 wbs values to CJ30

Former Member
0 Kudos

  Dear Experts,

My cost Planning values for WBS same as budgeting.

How can I transfer my plan values from T-code CJ40 to T-code CJ30.

Please suggest,

Thanks,

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

CJ30->Open Project->Select the required WBS elements->Menu bar->Edit->Copy View->Select Option 5(Planned Total)->Give 100 if asked for percentage->click on continue icon.

Check if your Planned values will get copied to Original Budget. Then select Budget column->Edit->total up->save.

Also you can use IMCCP3 tranx to copy plan values as suggested above.

Regards

Shishir

Former Member
0 Kudos

Thanks, Issue Closed.

Answers (3)

Answers (3)

Former Member
0 Kudos

Hi,

There is T-code IMCCP3, it works as transfer Planning cost of CJ40 to budget in CJ30.

Former Member
0 Kudos

Hi,

You can use transaction IMCCP3 to transfer plan to Project budget.

regards

Ali

former_member213716
Participant
0 Kudos

Hi Pawan,

You can copy the Cost Plan of CJ40 in to Budget CJ30,

Go to CJ30, open Project,

Select all WBS -> go to menu option -> Edit -click on Copy View - Select Planned Total

Maintained Percentage if required

This will copy the Cost Plan Value in Budget.

Pls try , if face any issue pls revert

Rgds

rajesh