Subcontracting without 57f4 challan

Dear Guru's

I have scenario , Industry is textile industry...  as product is non Excisable and going for subcontracting my doubt is.

1. as we are transferring material by mvt type 541 to vendor ,Is there need to send material by 57f4 challan by using t code J1IF01 , because transactions are increasing in this case.

2. if i am not using t -code J1if01 ,and sending material by taking 541 document print out , how to generate reconciliation report against 541 material documents.

Thanks & Regards.

Akshay

Former Member
replied

Hi,

   The 57F4 challan is applicable for excisable goods only as per legal rule in India. May I know what you want to reconcile in case of non-excisable goods. If you issue the goods against PO number in MB1B (541 movement), then only you can track the stock based on PO in ME2O.

   For sales order stock in subcontracting, refer the help doc: Subcontracting for Sales Order Stock and Project Stock - Managing Special Stocks (MM-IM) - SAP Library

Regards,

AKPT

0 View this answer in context