on 05-05-2014 10:24 PM
Greetings
Our business process sometimes requires billing to happen prior to PGI.
Hence, we have modified copy control settings to allow billing based off delivery creation (rather than PGI delivery).
No modifications to the item categories and we are using standard movement types 601/602
My issue is at VL09.
VL09 will not allow me to reverse without cancelling the billing document.
I get a message No data available for these selection criteria
I have checked OMJJ movement type settings and I dont see anything here.
Can anyone point me in the right direction to customize such a setting if it exists?
We are using ECC 6.0
thank you
Ken
hi
your issue as standard behavior , when delivery document billing status completed , you can not do the PGI , when you cancel the billing document then only system will accept PGI ,
when you cancel the billing document , delivery document billing status will change , so accept PGI
this status comes based on billing document types , like final billing (f2) delivery billing status comes complete, proforma invoice completed then delivery billing status comes not yet proceed
this is the why system not accept the PGI for final billing document done
check proforma billing document delivery PGI
Regards
sankar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear .. Could You explain A little bit more please i didn't get Your requirement
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
85 | |
7 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.