Message no. DPR_FIN_GECCO024 Error occurred in accounting - see link controlling cockpit (cProjects)

Hi, everyone

I'm integrating PS( which is on IDES system ECC6 PH6) with cProjects( which is on DEV system ECC6 PH6 PPM 5.0). I've done customizing in DEV and IDES. The Controlling Method is Multilevel Controlling (Structure Element, Automatic).

When I'm saving a project with status 'to be transferd', the warning message appeared and I'm failing to assign PS Project automaticlly. But manual assignment works fine.

Error occurred in accounting - see link controlling cockpit (cProjects)

Message no. DPR_FIN_GECCO024

Diagnosis

Errors occurred when transferring to accounting.

System Response

DPR_FIN_GECCO 024

Procedure

Choose the Controlling Cockpit (Project Management) link on the Accounting tab page. In the cockpit, you can create a variant with your Project Management project under Selection Variant Orders Project Management. The errors that occurred are then displayed. If no messages are displayed in the controlling cockpit, they have already been processed or deleted. If this is the case, trigger the transfer again.

No more messages are displayed once the transfer has been carried out successfully (that is, no errors occurred).

Here is the problem:

In this Message, I was told to Choose the Controlling Cockpit (Project Management) link on the Accounting tab page. But actually, I can not find the Controlling Cockpit (Project Management) link on the Accounting tab page. It was missing.

I don't konw what‘s the problem with the missing Controlling Cockpit and how to deal with this warning message getting automatic PS assignment done.

By the way, I've done IDES test, cProjects and ERP system were integrated on the same system with RFC destination NONE. And that works fine on IDES, so I guess I've done the right customizing in the ERP system( IDES).

Best Regards,Yemi

Tags:
Former Member
replied

Hi Yemi,

Controlling cockpit is accessed to view the error details in the accounting integration. This can be accessed through two ways.

1) In Project-->Accounting tab

2) Through tcode - COCPCPR

You can try the second method to view the error details.

And coming back to your query on project profile config in PS, as Pramod said, by standard SAP delivers a standard profile in SAP PS for cProjects-->PS integration. You can find the same in the below SPRO path.

Project System-->Structures-->Operative structure-->Work Breakdown structure(WBS)-->Create Project profile

Project profile name : CPR0001

This project profile is used when an automatic PS project is created through accounting integration.

Hope this helps.

Regards,

Ravi