we plan to use contracts as source of supply , we created some contracts in ECC and CIF successfully to APO system , although they are visible in APO side in  external procurement relationship , they are not visible during interactive mode on the SNP planning book with Distribution receipts.

we also notices that source of supply ( contract)  it is visible from /SAPAPO/RRP3 while creating order.

can anyone please let us know if they have similar behaviour for  Contracts

we are currently on SCM 701

Accepted Solutions (0)

Answers (1)

Answers (1)

rupesh_brahmankar3
Active Contributor
0 Kudos

Hi Ashfaq,

Please refer OSS note  1527190 - SNP-Interactive Planning ignores contract

Regards,

R.Brahmankar

AA3
Participant
0 Kudos

we checked it earlier , it cannot be implemented on our system.

AA3
Participant
0 Kudos

the prerequisite 1100390   shows not released .

rupesh_brahmankar3
Active Contributor
0 Kudos

Hi Ashfaq,

I was taking about OSS note 1527190 - SNP-Interactive Planning ignores contract

If you are not able to implement the OSS note then do the manual correction given in note.

* In case of Contracts #1527190 AH

  IF ls_poco-locfr IS INITIAL AND ls_poco-plobid = gs_c_standard_tables-matlaneco.

  ls_poco-plobid = gs_c_standard_tables-matloc.

  ELSEIF ls_poco-locfr IS NOT INITIAL AND ls_poco-plobid = gs_c_standard_tables-matlaneco.

  ls_poco-plobid = gs_c_standard_tables-matlane.

  ENDIF.

* #743961 In case of scheduling agreements it is sometimes (OLTP).

Also raise OSS message.

Regards,

R.Brahmankar