Hello,

I have a customer that needs the following and I can't find a way to do this.

1. Create Master BOM in ECC, with sub-items(refdes), attached to Material Master

2. Create Production Order in ECC

3. Make changes to Production Order BOM Sub-Items(refdes)

4. Release Production Order and it is sent to ME via MEINT

I can't find a way to edit or change the sub-items in the Production Order so that I can change the refdes.

Rusty

Accepted Solutions (0)

Answers (1)

Answers (1)

0 Kudos

Hi Rusty,

I would try asking this question in SCN PP Space http://scn.sap.com/community/erp/manufacturing-pp/contentas the changes need to be made on ERP side.