on 04-30-2014 1:50 PM
Hi ,
I have requirement to attach single BOM material component to multiple activities through transaction CN33.
As I checked in system when I attach the same BOM to another activity in a project system reassigns the material.I explored the functionality with the help of reference point but it is not working.
Please suggest.
Best Regards
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Can you please be a little more clear on your issue. SAP provides solution through reference points to assign different material components under a BOM to different NWA.
Is this not working?
thanks
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Thanks Mos ,
I am using reference point but my requirement is I need to assign a single bom to multiple activities
say I am having BOM1 and there are Five activities in a Network 0010,0020,0030,0040,0050
I want to assign BOM1 with all components to all Five activities
Activity 0010
-- BOM1
Activity 0020
-- BOM1
Activity 0030
-- BOM1
Activity 0040
-- BOM1
Activity 0050
-- BOM1
Currently system is not allowing me to assign BOM1 to only one activity in network in CN33.