on 04-24-2014 3:08 PM
HI
I am facing serial number issue after doing PGR
i am into STO process . Oce PGI for outbound delivery is created and then MIGO (PGR) will happen at recveing pant
issue is after MIGO (PGR) the serial number status must be in AVLB ..but it is still in EDEL ESTO ...
The AVLB status must come automatically in the equipment master.
How did you do the MIGO? Against PO? Try to do the MIGO against delivery and check.
Also check the serial number profile in IQ02/IQ03, whether any plant is assigned to it or not.
Regards,
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
I am doing through PO...we don't have inbound delivery process ... so i do MIGO with reference to PO
We have equipment master IE01/2.. plant is assigned after MIGO reeving plant is getting updated in the equipment master but the serial number status is not getting changed to AVLB.... also the serial number profile is with MMSL procedure.