Planning run with CTM SNP

former_member232086
Participant
0 Kudos

Hi Team,

Please for your help for the below issue in SNP CTM.

we have two plants for finished product one location (x) and semi finished items location is Y..when we are creating orders in the location x and if there is not stock..planned order should create in Y...

But when we are running heuristics in /n/sapapo/sNP94 it is creating correctly..but when we are running CTM planning, the distribution receipt is creating after 10 days... but if we can stock in stock Y then the distribution receipt is creating correctly..

Any idea why is happening ? thank

Accepted Solutions (1)

Accepted Solutions (1)

abhay_kapase
Active Participant
0 Kudos

I believe, 10 days are because of stock transfer horizon.

I am just guessing over here, in case of Heuristics, you must be planning finished product only.

While CTM plans for entire supply chain. CTM may not have found supply available for semi finished product and is trying to procure it. Hence, distribution receipt is getting created after Stock transfer horizon.

Abhay

former_member232086
Participant
0 Kudos

thanks for the help..

need one more help..how to change the stock transfer horizon?

Thanks,

Vijesh

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi vijesh.

go to //mat1

in SNP 2 tab, under SNP supply profile you can change stock transfer horizon.

rgds

Raja kiran R