on 04-22-2014 5:29 PM
Hi,
This is an in-house production scenario. SNP planned order are created based on forecast, now i want to convert those SNP planned orders to PP/DS planned orders in product view. While converting i am getting the following error message.
Message no. /SAPAPO/RRP707
I have checked the SNP, PP/DS PDS, it looks good.
Regards,
LV
Hi LV,
This usually happens if the material has a make-to-order scenario (Planning without final assembly). What is your planning strategy?
Or due to missing/valid sources of supply in PPDS. Are you able to create manual PPDS order?
Is this problem with one material or all?
Regards,
R.Brahmankar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Brahmankar,
Thanks for your update.
Planning strategy is Make To Stock 40. This problem with header materiel, i have 5 levels of products below. Source of supply is correct for all materials.
1. I am able to create PPDS order trough product view.
2. SNP Planned orders created correctly trough SNP palnning book, then change the source of supply manually in product view that time system able to consider PPDS source of supply.
Regards,
LV
Hi Lingaiah,
When orders are read from the livecache and an error occurs there e.g. an
unknown pegging area due to inconsistencies. Check the OM17 consistency check.
Delete old SNP orders and create new orders and try to convert it.
Also check the Global parameter setting for conversion in SPRO--Advanced Planning and Optimization--Supply Chain Planning--Production Planning and Detailed Scheduling (PP/DS)--Global Settings--Maintain Global Parameters and Defaults
Heuristic Conversion SNP->PP/DS and Conversion Rule.
Regards,
R.Brahmankar