We have a requirement where we want that while creating the sales order Product allocation check should occur first then ATP check in ECC we do not have APO system here.
Is there any configuration settings or any user exits are available to achieve the same ?
Thanks,
Vinay
Hello Vinay,
As per standard SAP R/3, depending on settings maintianed in the scheduline category and requirement class, first availability check is performed and then confirmed quantity from ATP will be checked against product allocations. If no quantity is confirmed from ATP, check against product allocations also failed even there is sufficient product allocation quantity. In SAP R/3 your required functionality is not possible. Product allocations will be done based on ATP quantities.Can you please recheck the business requirement why Product allocations first and then ATP check.
Warm Regards
Siva B
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Can you let me know whether currently, it is happening or not? For information, in IMG, SAP has given a provision through which, availability check will happen against product allocation. Please test and update here.
G. Lakshmipathi
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Two exits are there EXIT_SAPLQUOT_001 and EXIT_SAPLQUOT_002 which are related to Product Allocations but I am not sure, how far this would be helpful to you. I think, if business process warrants you to deviate the standard functionality, then it is better to raise an OSS message.
G. Lakshmipathi
User | Count |
---|---|
88 | |
7 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.