Dear Experts,
I have a Project and not using any budget profile, already actual data exist only in CJI3 no data in CJI5.
Now I assigned Budget Profile in that project.
While entering Budget in T-code CJ30, I can see values in assigned values for a wbs elements.
Example -
WBS Element - XXXXXX-02 - 2000 (Assigned) - Here Budget Profile not assigned in the project
Same WBS Element - Once Budget Profile assigned, when am assigning same 2000 budget am getting budget exceeded issue.
If I give 2500 I am not getting any errors, My tolerance as only Warning message.
Please Suggest - Screenshot attached
Thanks,
Hi,
Go to -T code OBMSG -- select BP - click on messages 608 - and make as a Warning or Switch off -
go and Use CJ30 system will allow to save
Thanking you
Mahesh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Pavan,
As soon you enter your budgeting fig the availability control triggers, this check your assignment with available budget.this the reason you are getting error as you say there are already actual posting in CJI3.In this you need to balance first the fig which is appear in assigned column in CJ30.
Its a good practice to give budget first release it & then start procurement,confirmation etc.
Check this in budget profile availability control.
Regards,
Sachin.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
91 | |
8 | |
7 | |
4 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.