on 04-18-2014 4:31 AM
Hi,
I tried to update the PIR of last several monthes, but it can't be transfer to APO.
is this the standard behavior of system?
How to remove if the old PIR is not availble?
Thanks.
Hi Geoffrey,
In standard SAP it is not possible to transfer back date PIR to APO you can only have future period PIR. Planned independent requirements into the APO only takes the date of the requirement time stamp into account. You can deleted the PIR in ECC by using MD62, MD74 or MD75.
Also check enhancement CIFPIR02 for Transfer of Planned Independent Reqs to APO.This user exit is called in function module CIF_PIR_FILTER.
Regards,
R.Brahmankar