Wrong committement item in PO - posted on behalf of Preeti K

marlyn
Advisor
Advisor
0 Kudos

Hi,

User assigned wrong commitment item in PO,  so posted value is sitting in different fund center which is differ from PO.PO is done as stock transfer from one dept to other dept.  Now the user want to post to correct commitment item. Actually this posted done in Sept , OCt , Nov 2013.

Can you suggest the solution for this. How to transfer to this value.

Regards,

Preeti kadkol

Posted by moderator on Preeti's behalf

Please post discussion, mark as question, in future. Thank you.

1 REPLY 1

Former Member
0 Kudos

Hi,

Correct PO with t.code FMCN and FMCT to actual FC and CI.