Dear QM Experts,
I have activated the Auto UD checkbox in Material master for a material.
When I create a Inspection lot & enter all the characteristics in QE53N, I select all & evaluate.
If all pass, then after evaluation - the lot shud automatically change to UD status sine Auto UD selected ?
However, the lot is still in rel status till we manually change it to UD to post goods mvmnt.
Pls guide me how to solve the above scenario so as the lot automatically changes to UD status after evaluating in QE53N (provided all data pass).
Thanks
Mudassar
SAP PM/QM Consultant.
If i put the time as zero hrs & zero min wating time - do i still have to run the variant or UD will be done immdtly after valuation.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
For automatic usage decision you have to do the following.
The automatic usage decisions are carried out by a program that is executed periodically by the job management function.
A job must be created for this purpose which is repeated at various intervals
To answer you question, you have to schedule / execute the job for automatic UD.
Thanks,
Dear SM,
Please go through this....
The system can only make an automatic usage decision if the following conditions have been met:
No characteristic has been rejected in the inspection lot
All required characteristics have been confirmed and closed
No defect records exist for the inspection lot
An automatic usage decision has been planned for the material
The automatic usage decisions are carried out by a program that is executed periodically by the job management function.
If you want to use the function for the automatic usage decision, be sure to consider the following points:
The parameters for the automatic usage decision is defined in the Customizing application. In the QM plant settings, you define the time interval that must expire after an inspection lot is created and before an automatic usage decision can be made.
Use Programme RQEVAI30 from Auto Usage decision. CREATE variant fot it and schedule it.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Use the T.code QA17 to schedule the jobs for Auto UD , Based on the time given in Plant dependent QM settings & preconditions given by Mr.Saurab Kumar system will pick the lots for UD as schedule.
SPRO-->QM-->Basic settings-->Maintain settings at plant level-->select the plant-->InsLot Completion tab-->Automatic Usage decision.