on 04-16-2014 11:03 AM
Actually we are going through implementation of SAP Project system, i would like to ask whether there is an option in SAP PS to set different working/factory calendars and use them for individual activity like Primavera. Because at some places there is 5 days working and at places 6 says working. Also holidays are different for different people/places. A uniform calendar for all activities can spoil the schedule of project in regard of planned finish dates when one enters a certain duration.
Kindly clarify this for me
Regards.
Hi Abdul,
As a reference, go through this thread,
Factors Influencing Scheduling - Dates - SAP Library
In addition to this and as mentioned above by Saurabh, there are some good threads available that talk about this. The threads carry a good amount of information and am sure it will help you.
Please search the forum.
Best Regards,
Gokul
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
It's possible to use plant calender,factory calender,work center calender in projects. There is a predefined level also of them. Please search more on it in the forum. There are some good threads on its use,application and priority.
Thanks
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Abdul,
Further to what Sanjeev has added after making the required changes using scal transaction, if at all the business wish to analyze the activities for which different factory calendar id's have been assigned within the same project you can differentiate the activities based on control keys as well.
Please let me know if this helps you,
Regards
Varun
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Abdul
You can assign different factory calendar's at activity, work center, plant.
For scheduling purpose the activity factory calendar have priority over work center factory calendar. and work center factory calendar have priority over Plant Factory Calendar
vijay
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Adbul,
As stated by others, you can have different Factory calendars and assign them to work centers separately
At activity Level you can't Maintain different Factory Calendars, it can be done only at work center level
Hope it is clear
thanks
santosh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi...
when defining internal activities in the project you use a work center. Therefore you can work with the calendars of each one of the work centers you have in your project and manage them accordingly.
Hope it helps
Panagiotis
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Not sure but you can execute SCAL transaction where you can create and assign holiday or working days and non working days then use new created factory calendar when you going to create project in project builder logically it should be work first test it cos i never tested it before.
Regards,
Sanjeev
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
91 | |
7 | |
7 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.