validation on settlement rule percentage

Former Member
0 Kudos

Hi folks,

We have a requirement to set up a validation on the settlement rule percentage for an IO/WBS which settles to a final asset to restrict it to 1% or greater. In other words the settlement rule to final asset below 1% should not be permitted. Could you please suggest if this is doable?

Thanks!

Accepted Solutions (0)

Answers (2)

Answers (2)

sanjeevc
Active Contributor
0 Kudos

HI Manish,

Give conditon like if COBRB-PROZS = >1% (have less then or upto 1% then) system should not allow to execute settlement.

Regards,
Sanjeev

former_member195427
Active Contributor
0 Kudos

Hi Manish,

You have two ways to check for it:

1. Check for Exits in WBS validation.

2. Check BADI WBS_SETTLEMENT_RULE. With this you can automatically populate the settlement rule based on project type.

Regards

Saurabh

varshal_kachole3
Active Contributor
0 Kudos


Hi,

Please try the User exit in Validation.

Hope it helps!

Thank you and Regards,

Varshal Kachole