on 03-22-2007 9:36 AM
Hi SRM gurus,
We have created a shopping cart for services whose requirement date is in the past.
Now the manager cannot approve as he didnt do before the requirement date and the requestor cannot change as the req. date is in past.
The error message standard 588, we changed to warning but it is not working for services, still throwing the the same as error message.
Any suggestions/solutions.
Reg.,
Sridhar.
Hi
I guess this OSS note will help.
Have a look ?
Note 976533 - Changing the "Required on"/"Start Date" in shopping cart
Regards
- Atul
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Did you already checked OSS note 768091?
Kind regards,
Yann
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.