on 04-13-2014 9:26 AM
Hello folks,
recently we have activated SM service desk and it really is a great tool !
Yet there are some anoying issues which I couldn´t fix.
- We have defined 4 Status New / Service desk action (In progress) / User Action(Solved) / Finished. Is there a way to force a automatic status change ?
It is often the case that a incident is solved and set to User Action, now the user adds a command but does not change the status back to in progress.
As a result no mail to the responsible consultant is triggered.
Moreover it would be handy if Incidents which are 2 Months on Status User Action are automatically set to status finished.
-
Hi Matthias,
Yes it is possible with below report
AI_SDK_SP_AUTO_CLOSE2
this will resolve ur issue
Thanks
Prakhar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Thanks for the Help guys!
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Matthias,
Please check and follow my blog:
Solman - Set Up Automatic Confirmation / Changing User Status of
Messages using report: AI_SDK_SP_AUTO_CLOSE_2
http://www.sdn.sap.com/irj/scn/weblogs?blog=/pub/wlg/27920
Thanks
Vikram
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
87 | |
10 | |
10 | |
10 | |
7 | |
6 | |
6 | |
5 | |
5 | |
4 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.