Budget not checked in collective release of service entry sheets.

Former Member
0 Kudos

Hi,

A service purchase order created on FY2013 with real fund center and commitment item, budget was consumed but open commitment item does not carry forward to FY 2014.Now user created service entry sheet and collective release it with t.code ML85. where budget was zero for FY2014 but system does not check budget make negative entry. How it is possible ??

Regards,

Rabin.

3 REPLIES 3

iklovski
Active Contributor
0 Kudos

Hi,

A good receipt (or service sheet entry) does not trigger availability control in a standard system design. If you want to do it, you have to implement note 142866.

Regards,


Eli

Former Member
0 Kudos

Hi Eli,

My basic issue is no payment budget value should be exceed than commitment value, like MIGO,SES,MB01,ML85 and ML81N value should be check available budget before post document.so that budget should not be negative. This is the critical requirement of my client.

system: EA-PS, release 600,SP level 24. Budget with BCS

Please recommend, Is above note applicable?

Regards,

Rabin.

iklovski
Active Contributor
0 Kudos

Hi,

Yes, you can implement this note in order to activate AVC on MIGO. Otherwise, there is no check...

Regards,

Eli