cancel
Showing results for 
Search instead for 
Did you mean: 

Forecast not disaggregating properly

lalit_behere
Explorer
0 Kudos

Hi,

We calculate forecast on monthly level and disaggregating it to week level.

We follow Calendar year 4, 4 and 5 Weeks.

Year 2015 has 53 Weeks so in DEC 2015 we have 6 weeks. ( As per our design).

1. When our Monthly-Forecast Process Chain ran, for month "DEC 2015", forecast got disaggregated into 1st 4 weeks and the last 2 weeks were populated with "0".

Example:

MonthlyDec-15
Monthly6000
Weekly150015001500150000

2. Checked in Dev: when values entered in Development for DEC 2015 it is properly getting disaggregating into 6 weeks. It reflects that the disaggregation Macro is working correctly.

Example:

MonthlyDec-15
Monthly6000
Weekly100010001000100010001000

3. Secondly: When I ran the macro manually in Production for DEC 2015 and re-disaggregated the forecast it gets populated correctly to all weeks.

But in the next run of our Monthly-Forecast Process chain the "0"s were shifted to last 2 weeks of next month i.e. JAN 2016.

Example:

MonthlyDec-15Jan-16
Monthly60005000
Weekly1000100010001000100010002500250000

Regards

Lalit

Accepted Solutions (0)

Answers (1)

Answers (1)

former_member182607
Active Participant
0 Kudos

Lalit,

I need more details...are you using fiscal periods? How are you doing the time based disaggregation?

Thanks,

Subash

lalit_behere
Explorer
0 Kudos

Hi Subash,

Yes we are using Fiscal Periods. As  I stated we follow a 4, 4, 5 weeks pattern in a year.

For Time based disaggregation we are using another key figure which is again based on another key figure for Time based disaggregation and for this we are calculating the proportions on the basis of Demand History Override ( manual entry)

Key FigureCalculation typeDisag, KFTime Based Disag.Time Based Disag. KF
STATPPROPFNLKTIMEFNL
TIMEFNLS KPROPFNL
PROPFNLPAPODPDANT

Regards