Report for tracing the Appropriation Request

Former Member
0 Kudos

Hi!

In the case of Projects created in the background after approval of the Appropriation Request-Do we have any report wherein we

can trace the related appropriation request number if we know the project code? (like ME5J or ME2J for PRs and POs)

Thanks in advance

Prasad

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi Prasad,

Our users also had the same requirement but I could not find standard report.

So I did a simple SQVI report joining PRPS & IMAKZ tables.

Another way,

Simply you can find the appro.request(AR), just open project in CJ20N

->select the WBS that link AR.

-> CRT+shift+F4( Menu Edit->WBS element-> Investment Progrms.->Investment program)

->then infor message come & click in question mark to see infor, there also system gives the AR that related to current WBS.

Hope those would help you out.

regards,

Sam..

Answers (2)

Answers (2)

former_member195427
Active Contributor
0 Kudos

Hi

You can get it in Audit Trial: Transaction- AUT10.

Give start date and end date -> Enter t-code IMA11  -> Execute

Now, filter the output data for table IMAKZ. It will give you the projects/orders object number assigned with AR.

Regards

Saurabh

Former Member
0 Kudos

Hi,

Can you please check IMA11. Not sure whether it will suit your requirements.?

Regards,

Amit