New and old Solution Manager in parallel - how to manage transition?

Former Member
0 Kudos

Hi all

We set up a new Solman 7.1 SP11 in parallel to our old Solman 7.0

We connected some of our systems to the new solman 7.1 (SLD, DAA, Managed Systems Configuration), but during transition e.g. our productive Systems must remain in the old Solman.

How do I deprovision these systems completely from our old Solman so it does not send/fetch data to/from the systems or to SAP Marketplace?

BR

Michael

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

The best would be to set up a SLD data push from your old to your new Solution Manager. This way, you can fill SLD and LMDB in advance and switch fast to your new system.

When you want to disable your old SolMan, just deactivate the jobs (e. g. using BTCTRNS1), most important jobs are

REFRESH MESSAGE STATUS

REFRESH_ADMIN_DATA_FROM_SUPPORT

SEND_SYSTEM_RELATIONSHIP_TO_SUPP

SERVICE_CONNECTION_LISTENER

SM:SELFDIAGNOSIS_SEND_TO_SAP

SM:SEND_SOLUTIONS_TO_SAP

I suggest deactivating all jobs and change batch processes to 0.