Hi! Can anyone give me a hand on this issue?

Is there any way to input planned delivery quantity on a delivery (VL01N)? This quantity should not have any impact on the ordered quantity and on the stock movement. Besides that, it should rest unchanged after the goods issue.

Accepted Solutions (0)

Answers (2)

Answers (2)

phanikumar_v3
Active Contributor
0 Kudos

Sir--thanks for the Clarification on Planned delivery quantity--My doubt rectified.

Phanikumar

Lakshmipathi
Active Contributor
0 Kudos

No not possible with standard functionality.  May be you need to develop a zee table where you can store such changes via a Delivery exit but for that also, it is possible only if you have activated Picking functionality.

G. Lakshmipathi

phanikumar_v3
Active Contributor
0 Kudos

Sir-Planned delivery Qty!!!!

where i can see this--unable to find in LIKP/LIPS...

Phanikumar

Lakshmipathi
Active Contributor
0 Kudos

Normally planned quantities would be maintained by PP in MC93.  From SD side, you can consider order quantity as planned delivery quantity which you can see in VBAP table.   If you want to see quantity break up for different delivery dates, then, you can check in VBEP  where also, you can see Order quantity field