Hi Team,
Need your support in below issue.
I want to use "Change Documents" log feature for below fiels in Project System WBS Element.
BscStart (WBS element: Basic start date (PRTE-PSTRT))
Bsc Fin (WBS element: Basic finish date (PRTE-PENDE))
I have activated the "Change Documents" check box at data element level (using access key)
However still CN60 not showing change to dates in wbs Element.
Is there any other step which I missed.
Please suggest.
Warm Regards
Krishan
Hi Krishan,
Go to OPSA and check Control Tab for Project profile that you are using.
Change documents checkbox should be activated...
Please check this once.
Regards
Tushar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
95 | |
11 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.