What is the difference between Commitment, assigned, actual and available in the shopping cart process? Also what are the different commitment stages?
Hi Tejas,
Is these terms related to WBS Budget ?
If yes, then they are just general terms FI use in WBS.
Actual : Actual budget assigned to WBS
Assigned : Budget consumed after SC is approved and PO is created
Committed : Budgete assigned to a SC or PR (PO not created)
Available : Available budget (Actual - Assigned - Committed)
Best Regards,
Anil
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Tejas,
where have you seen these texts.
Could you please provide screenshots
Regards
Konstantin
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.