0 Kudos

We will be setting up suppliers to use SMI.  In our ECC system, we will have purchase contracts by plant, but PIRs by Purchase Org (so a PIR can span multiple plants).

When a supplier creates a Replenishment Order in SNC, how will the resulting PO determine pricing?  Will it look at the PIR, or will it pull the price from the contract?

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi Sott,

System will pick the price from contract if you have created transportation lane by CIFing the Contract.(ECC to SNC)

Regards,

Nikhil

0 Kudos

Nikhil,

Thanks for your answer.  Just to make sure I'm clear - SNC will ignore the price on the Pricing Info Record, and take the price from the contract if both exist - is that correct?