Re-trigerring availability check in sales order

Former Member
0 Kudos

Hello,

I want to re-trigger availability check based on some critical field changes in sales order (like ship to party, delivery date etc ).

how to achive the same. ?

regards

Pamela

Accepted Solutions (1)

Accepted Solutions (1)

Lakshmipathi
Active Contributor
0 Kudos

For such type of queries, please try on your own in your system, observe how system behaves and in that if you have any issue, please post here so that members will help.  In the past also, you have been asked not to post like this. 

Really if you want to learn SD process, unless you try on your own, but expecting others' assistance, it will be very difficult for you to come up in the ladder.

G. Lakshmipathi

Answers (2)

Answers (2)

former_member219259
Participant
0 Kudos

Hi Pamela,

Noel is right that if you change ship to party or delivery date, ATP will again be executed.

If you want to do it manually, you can goto sales order. delete the schedule line and then goto Edit- Item Availability to carry out ATP again.

Regards,

Aayush Jain

SAP SD Consultant

former_member223981
Active Contributor
0 Kudos

Hi Pamela,

Usually, an ATP check is automatically triggered when ATP relevant changes are made. For example, if you change the "Ship - to" party, an availability check will be executed.